Ongoing Hydro Projects Allotted to Private players in the Country
Given below is the list of Ongoing Hydro Projects Allotted to Private players in the Country – Benefits during 11th Plan
(Excluding Projects upto 25 MW Capacity under Ministry of New and Renewable Energy)
| Name of ProjectCapacity/
Agency/ Date of approval |
Installed Capacity(MW) | OriginalSchedule | Latest Expected | Reasons for delay |
| Karcham Wangtoo(4×250 MW) H.P.
M/s. Jaypee Karcham Hydro Corp Ltd.,(JKHCL) 31.3.03 (TEC) |
1000 | Mar-2010(2009-10) | Nov-2011(2011-12) | Delay in Financial closure.Delay in start of works on right bank of Satluj due to agitation by local villagers. |
| Budhil(2x35MW) H.P.
M/s. Lanco Green Power Pvt. Ltd. NA 02.06.06 |
70 | Dec-2008(2008-09) | June- 2010(2010-11) | Slow progress of HRT due to poor geological conditions.Slow progress of dam works. |
| Malana-II(2x50MW) H.P.
M/s. Everest Power Pvt. Ltd. 15.10.2004 (State Govt) |
100 | July-2009(2009-10) | Mar-2010(2009-10)
Likely to slip to 2010-11 |
Poor geology in HRT.Power evacuation arrangement. |
| Srinagar(4×82.5 MW)
Uttaranchal M/s Alaknanda Hydro Power Co. Ltd. 14.6.2000 (TEC) |
330 | Oct-2005(2005-06) | Oct-2011(2011-12) | Delay in Financial Closure. |
| Maheshwar(10×40 MW) SMHPC M.P.
30.12.96 |
400 | Mar-2002(2001-02) | Mar-2012(2011-12) | R&R problem,Funds constraints. |
| Teesta Stage III(6X200 MW) Sikkim
M/s Teesta Urja Limited 12.05.2006(TEC) |
1200 | Oct-2011 | Mar-2012(2011-12) | Delay in forest clearance |
| Allain Duhangan(2x96MW) H.P.
M/s. AD Hydro Power Ltd. 20.8.02 (TEC) |
192 | June- 2008 | Mar-2010(2009-10) | Poor geological strata in HRT. Delay in Forest clearance of transmission lines from MOE&F. |
| Chujachen(2×49.5 MW) Sikkim
M/s. Gati Infrastructure Ltd. 30.11.04 |
99 | Sept-2009(2009-10) | (2010-11) | Slow progress in some stretches of HRT due to poor geology. Flash flood occurred on 16.04.09 at Rangpo dam. Coffer dam washed away. |
| Sorang(2×50 MW), H.P.
M/s Himachal Sorang Power Pvt. Ltd. 23.09.2004 |
100 | (2012-13) | Nov- 2011(2011-12) | As per schedule. |
| Total | 3491 |
Related posts:
- List of Hydro projects under execution – July 2009
- Tehri Hydro Development Corporation Limited – Koteshwar Hydro Electric Project, 4×100 Mw
- Teesta Low Dam Hydro Electric Project Stage-III 4×33 MW
- Lower Subansiri Hydro Electric Project 8×250 MW
- Parbati Hydro Electric Project Stage-II 4×200 MW
- Sewa-II Hydro Electric Project 3×40 MW
- National Hydro-Electric Power Corporation – Loktak Downstream Hydro Electric Project 3×30/2×33 MW
- Chamera Hydro Electric Project Stage-III 231 MW