Global Investors Meet

Latest Update !!! – MoUs signed on Day One of Global Investors Meet KarnatakaClick Here

Industries Department of Karnataka is organizing an investors meet on June 2nd and 3rd. The objective of the event is to invite and facilitate project promoters and entrepreneurs to invest in the state. Several Players in Power, Infrastructure, Sugar, Chemicals, Oil & Gas, Information Technology, Biotechnology etc., have evinced interest in setting up new projects in the state.

For More details, visit : http://www.advantagekarnataka.com

The proposed event, Karnataka Global Investors Summit 2010 will see a host of established companies and entrepreneurs signing Memoranda of Understanding with the state government for setting up of projects worth several lakh crores.

Click below for a snapshot of projects to sign MoU in the forthcoming Investors Meet.

Aerospace Projects

Cement Projects

Steel Projects

Oil & Gas projects

Sugar Projects

Other Projects

I am pleased to inform the readers that I have an invite for participating in the event and I am planning to do a Live Coverage of important events like project announcements, signing of MoUs from the venue.

I have put up a website , Karnataka Industry Monitor – for this purpose, from where you can get live updates on the events. I have also set up a special twitter a/c which also will be updated regularly on days of the Summit.

If you are interested in project related developments in Karnataka, watch out my blog and twitter.

Regards
S.Jaya Prakash.



  • a) Establishment of 765 kV pooling station in Tuticorin (initially charged at 400 kV)
  • b) Tuticorin pooling station – Tuticorin JV 400 kV D/c quad

Standing Committee Approval on : 29th Meeting on 27.08.09
Feasibility Report Submitted on : Nov,09
Investment Approval on : NA
Commissoning Schedule : NA
Status / Other Remarks :
-Feasibility Report prepared
-Investment to be taken shortly



  • a) Establishment of 765/400kV 2x1500MVA Pooling station at Nellore by LILO of Simhapuri Nellore 400kV D/c line
  • b) Nellore Pooling station Kurnool 765 kV 2x S/c
  • c) Kurnool Raichur 2nd 765 kV S/c line

Standing Committee Approval on : 26th Meeting on 13.06.08
Feasibility Report Submitted on : Nov,09
Investment Approval on : NA
Commissoning Schedule : NA
Status / Other Remarks :
-Feasibility Report prepared -Investment to be taken shortly

 



  • a) Extending 400 kV D/c of original Vallur TPS transmission system from LILO point to Malekottaiyur by suitably utilizing part of the LILO of Kolar-Sriperumbudur line at Melakottaiyur. Kolar Sriperumbudur 400 kV shall be restored as direct lines.
  • b) Establishment of Tiruvelam 765/400kV switching station initially charged at 400kV
  • c) Tiruvalam (POWERGRID) – Chitoor 400kV D/C quad line

Standing Committee Approval on : 28th Meeting on 15.06.09
Feasibility Report Submitted on : Aug,09
Investment Approval on : Feb, 10
Commissoning Schedule : Nov 12
Status / Other Remarks :
-Award to be placed shortly.

 



LILO of both circuits Gazuwaka-Vemagiri 400 kV D/c line at Simhadri-II.

Standing Committee Approval on : 28th Meeting on 15.06.09
Feasibility Report Submitted on : Nov,09
Investment Approval on : Jan, 10
Commissoning Schedule : Jul’ 11
Status / Other Remarks :
-Award placed in Feb’ 2010



  • a) Establishment of new 400/220 kV substation at Yelahanka with 2×500 MVA transformers and 1×63 MVAR bus reactor.
  • b) LILO of Nelamangla- Hoody 400kV S/c line at Yelahanka 400kV S/S
  • c) LILO of Somanahalli- Hoody 400kV S/c line at Yelahanka 400kV S/S

Standing Committee Approval on : 27th Meeting on 03.03.09
Feasibility Report Submitted on : July, 09
Investment Approval on : Feb, 10
Commissoning Schedule : Jul’ 12
Status / Other Remarks :
-Award to be placed shortly.



  • a) Establishment of new 400/220 kV substation at Chulliar (Palakkad) with 2×315 MVA transformers and 1×63 MVAR bus reactor.
  • b) LILO of both circuits of Udumalpet – Madakathara (North Trichur) 400kV D/C line at Chulliar 400 kV substation

Standing Committee Approval on : 25th Meeting on 28.03.08
Feasibility Report Submitted on : Oct, 08
Investment Approval on : Feb, 09
Commissioning Schedule : Jul 11
Status / Other Remarks :
-Implementation works are in progress

 



  • a) Establishment of new 400/220 kV substation at Bidadi with 7×167 MVA 400/220 kV transformers and 1×63 MVAR bus reactor
  • b) LILO of one circuit of Nelamangla – Somanahalli 400 kV D/c line at Bidadi 400 kV substation

Standing Committee Approval on : 24th Meeting on 18.06.07
Feasibility Report Submitted on : Sept, 08
Investment Approval on : Dec, 09
Commissoning Schedule : May’ 12
Status / Other Remarks :
-Award placed in Dec’ 2009



Hassan – Mysore 400 kV D/c line

Standing Committee Approval on : 24th Meeting on 18.06.07
Feasibility Report Submitted on : Aug,08
Investment Approval on : Feb, 09
Commissoning Schedule : Feb’ 12



LILO of Alamanthy Sriperumbudur 400 kV D/c line at North Chennai TPS JV

Standing Committee Approval on : 24th Meeting on 18.06.07
Feasibility Report Submitted on : Nov, 07
Investment Approval on : May 08
Commissioning Schedule : July 10
Status / Other Remarks :
-Activities in progress, Gen. likely by Feb 2011 as per 12th SRPC minutes

 