2×195 MW Muzaffarpur TPS Extension – Status Update

Implementing Agency : Kanti Bijlee Utpadan Nigam Ltd.- JV of Bihar SEB & NTPC Ltd.

Capacity : 2×195 MW extension at Muzaffarpur TPS

Coal Requirement : 2.20 MMTPA

Status :

  • Feasibility Report prepared and approved by Company Board. Estimated cost Rs. 2,918 Crores.
  • Unit size reduced from 250 MW to 195 MW as per aviation clearance of chimney height to 146.5 metres accorded by Airport Authority of India.
  • Coal linkage accorded by Ministry of Coal (MoC) from ECL for 2.92 MMTPA in December 08.
  • NTPC Ltd. is consultant.
  • State plan outlay amounting to Rs. 32.14 Crores has been approved by Planning Dept., GoB for the year 2009-10. Rs. 2.14 crores released to KBUNL in Sept. 2009.
  • Bids invited from BHEL for Main Plant package opened in July 2009. Negotiations are in progress with BHEL.
  • Water: Water Resources Dept., GoB has given consent for 45 Cusecs from River Burhi Gandak. Clearance from CWC awaited.
  • 100% generated power to Bihar/BSEB.

To be commissioned in : 2013-14

Address :
Kanti Bijlee Utpadan Nigam
Muzaffarpur Thermal Power Station
P.O Kanti Thermal
Dist. Muzaffarpur
Pincode : 843140
Email : dilipduttantpc@gmail.com
Tel : 06223-267315
Fax : 06223-267310

List of New Thermal Power Projects in India- - Download Free Report

Related posts:

  1. 2×250 MW Barauni TPS Extension – Status Update
  2. Status of the power projects proposed to be set up in Kodarma, Jharkhand
  3. RAJASTHAN ATOMIC POWER PROJECT 5 & 6, RAWAT BHATA
  4. Ultra Mega Power Projects – Current Status
  5. New Projects by NTPC – NIT Stage
  6. KPCL Plans Power Project in Chhattisgarh
  7. KPCL’s power project in Chhattisgarh
  8. Indira Sagar Polavaram Multipurpose Project (960MW)

No comments yet

Leave a Reply





XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

Switch to our mobile site