2×250 MW Barauni TPS Extension – Status Update

Capacity : 2×250 MW extension at Barauni TPS

Sector : State

Coal Requirement : 2.65 MMTPA

Status :

  • DPR prepared by M/s DCPL, Kolkata. Estimated cost Rs. 3066 crores based at prices in Jan-Mar’2009.
  • The Processing Fee of Rs 5 Lakh submitted to Ministry of Coal by BSEB vide letter no 682 dt 27.06.2006 for coal linkage. Coal Linkage awaited.
  • BHEL to implement BTG package (Boiler-Turbine-Generator) as OEM. Cost proposed Rs. 1,250 crores. BOP Package through different vendors in tendering mode.
  • BPIC – JV of GoB and ILFS is BSEB’s consultant.
  • State Plan outlay amounting to Rs. 180 crores has been approved by Planning Dept., GoB for year 2009-10.
  • NOC from Airport Authority of India has been obtained for chimney height of 275 meters.
  • Proposal to draw water from River Ganga for consumptive use. Water Resources Dept., GoB has accorded clearance for 60 cusecs for BTPS Units (existing and extension units).
  • Ganga Water Scheme: M/s WAPCOS is consultant. Interim report submitted. DPR under preparation and expected to be submitted by 31-01-2010.
  • 100% generated power to BSEB.

To be commissioned in : 2013-14

List of New Thermal Power Projects in India- - Download Free Report

Related posts:

  1. Status of the power projects proposed to be set up in Kodarma, Jharkhand
  2. KPCL Plans Power Project in Chhattisgarh
  3. Ultra Mega Power Projects – Current Status
  4. KPCL’s power project in Chhattisgarh
  5. RAJASTHAN ATOMIC POWER PROJECT 5 & 6, RAWAT BHATA
  6. Gas Based Power Plants – A Status
  7. 500 MW Khaperkheda Thermal Power Station – Status
  8. Indira Sagar Polavaram Multipurpose Project (960MW)

One comment

  1. Pawan Raj
    #1

    Pleasesend me the updates of power scenario of India.

Leave a Reply





XHTML: You can use these tags: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

Switch to our mobile site