Common Transmission System Associated with LTA Projects in Tuticorin Area-Part-A- Status Update
- a) Establishment of 765 kV pooling station in Tuticorin (initially charged at 400 kV)
- b) Tuticorin pooling station – Tuticorin JV 400 kV D/c quad
Standing Committee Approval on : 29th Meeting on 27.08.09
Feasibility Report Submitted on : Nov,09
Investment Approval on : NA
Commissoning Schedule : NA
Status / Other Remarks :
-Feasibility Report prepared
-Investment to be taken shortly