Status of Solar Power Projects in Gujarat

Given below is the list of ongoing solar power projects ( 10 MW and above) in Gujarat ( Solar Thermal and Solar Photo voltaic)

1. Moser Baer – Solar PV Project

  • Memorandum of Understanding signed with the Government of Gujarat for 600 MWp projects on 12th January, 2009
  • Project allocation of 3 x 15 MWp capacity has been received on August 1, 2009 by Government of Gujarat under Phase-I
  • Technology : Thin Film
  • EPC Contractor : In house.
  • Power Purchase Agreement : PPA has been executed . Under state policy, tariff of Rs.15/unit for first 12 years and thereafter Rs.5/unit from 13th year to 25th year has been approved
  • Transmission & Evacuation : GETCO to provide necessary infrastructure for evacuation of power from project site

Contact :
Moser Baer Solar Limited.
66B, SEZ Udyog Vihar,
Greater Noida (U.P.), India
Tel.: +91-120- 4658000

2. Adani Power – 40 MW solar PV power plant

  • Location : Surendranagar district
  • PPA Signed
  • EPC Contractor : Aries Waaree Solar, a joint venture between Aries Ingenieria y Sistemas, Spain and Waaree Group.
  • Tendering process for photo-voltaic technology-based equipment is underway
  • Project to be operational in end 2011.

Contact :
Adani Power Limited
Shikhar,
Nr. Mithakhali Circle,
Navrangpura,
Ahmedabad-380 009
Phone :+ 91-79-25557134
Fax :+ 91-79-25557177
Email : info@adanipower.com

3. PLG Power – 40 MW Grid Connected Solar PV Power Project.

  • Long Term PPA with Gujarat Urja Vikas Nigam signed.
  • Project Cost : Rs.8800 million
  • EPC Contractor : In house
  • The first 10 MW unit of the solar power project is scheduled to be commissioned by December 2010 and the entire project is expected to be commissioned in a phased manner, by December 2011

Contact :
PLG Power Ltd
139, A-1 Shah & Nahar Ind. Est,
Lower Parel (W), Mumbai- 400013 (India)
Tel: +91-22-42309500
FAX: +91-22-022-42309505

4. Lanco Solar – 35 MW Solar Power Project

  • PPA signed with Gujarat Urja Vikas Nigam
  • Current Status Not known

Contact :
Lanco Solar
Plot No 397 Udyog Vihar
Phase III Gurgaon 122016
Haryana, India
Tel : + 91-124 – 4741000 – 044

5. Cargo Power and Infrastructure Limited (a unit of Cargo Motors) – 25 MW Solar Thermal Power Project

  • Location : Rapar in Kutch district.
  • Letter of Intent received in August 2009.
  • PPA Signed with Gujarat Urja Vikas Nigam
  • Investment : Rs.650-700 crore.
  • The company has reportedly acquired 550 acres of land.
  • Financial Closure is expected in December 2010.
  • EPC Contractor : A Spanish and an Israeli firm will provide technology support and execution.
  • The project is also eligible for carbon credits, or CERs, for 10 years. The 25 MW Solar plant will generate CERs worth Rs3-3.5 crore annually. CERs will be shared between the company and the state government as per the agreed formula.
  • The plant is to be commissioned in end 2011.

Contact :
Cargo Power & Infrastructure (a Cargo Motors Enterprise)
Cargo House, Opp. Gandhi Ashram,
Ashram Road, Ahmedabad-380027
Gujarat, India
Website: http://www.cpil.co.in

6. AES Solar Energy – 15 MW Solar Power Project.

  • PPA Signed with Gujarat Urja Vikas Nigam

Contact :

AES Solar Energy Pvt. Ltd
9th Floor
Bldg 10, Tower B
DLF Cybercity
Gurgaon 122002
Haryana, India
+91 124 4300 300 tel
+91 124 4300 299 fax

7. Solar Semiconductor India – 20 MW Solar PV Power Project

  • PPA Signed with Gujarat Urja Vikas Nigam

Contact :
Solar Semiconductor India
Corporate Office and Manufacturing Facility
FAB City, Survey #114/P,
Srinagar Village, Maheshwaram Mandal,
RR Dist 501359, Andhra Pradesh
Phone: +91 40 67303000
Fax: +91 40 67303003

8. ACME Telepower – 15MW Grid Connected Solar PV Power Project.

  • ACME is setting up a 15 MW Grid Connected Solar PV Power Project using Crystalline/ thin film Solar PV modules.
  • Bids invited in July 2010 for supply of Transformers for 15MWp grid connected Solar Photovoltaic power project in the state of Gujarat.
  • PPA Signed with Gujarat Urja Vikas Nigam

Contact :
Acme Tele Power,
Plot 2, Sector 34,
Gurgaon
Email: manish.jha@acme.in

9. Azure Power – 15MW solar photovoltaic power plant

  • Investment : Rs.184 crore
  • PPA Signed with Gujarat Urja Vikas Nigam
  • The project will be jointly developed with SunEdison, North America
  • Power generation will begin by Jan 2011 with final completion expected by Nov 2011.
  • Once operational, this is expected to be the largest Solar photovoltaic power plant in India.
  • The investment is being led by Overseas Private Investment Corporation (OPIC), a U.S. Government agency. Additional investors include IFC, World Bank group and India and Foundation Capital.

Contact :
Azure Power
8, Local Shopping Complex, Madangir
Ground Floor, Pushp Vihar,
New DelhiĀ  110062
Phone – +91. 11. 49409800
Fax – +91 11. 49409807

10. SunBorne Energy – 15 MW Photo Voltaic (PV) project

  • Project Location : Kutch district.
  • PPA Signed with Gujarat Urja Vikas Nigam
  • EPC Contractor : Inhouse
  • In October 2010, IFC made an investment of US$ 10 Million ($4.1 Mn in equity and $5.9 Mn in quasi-equity instruments) in the company.

Contact :
Mr. Anil Nayar
Sunborne Energy
1st Floor, Technopolis, DLF Golf Club Road,
Sector 54, Gurgaon 122 002, Haryana India
Ph: +91 124 4750600
Fax: +91 124 4750601

http://sunborneenergy.com

11. Welspun Urja India – 15 MW Solar Power Project

  • PPA Signed with Gujarat Urja Vikas Nigam

Contact :
Welspun Urja India
Trade World, ‘B’-wing, 9th Floor,
Kamala Mills Compound,
Senapati Bapat Marg, Lower Parel,
Mumbai 400 013, INDIA

Tel :+91 22 66136000 / 24908000
Fax :+91 22 24908020 / 24908021

12. Astonfield Solar – 10 MW Solar Power Project

  • PPA Signed with Gujarat Urja Vikas Nigam

Contact :
Astonfield Solar Pvt Ltd
Mumbai Office
Maker Chambers V, Suite 916
Nariman Point
Mumbai 400 021, India
Tel: +91 22 6146 4000
Fax: +91 22 2202 9191

13. Millenium Synergy – 10 MW Solar Power Project

  • Project Location : Ahmedabad
  • Project Cost : Rs.200 crore
  • Project will be spread over 40 to 45 acres and will be undertaken in phases.

Contact :
Millenium Synergy Pvt. Ltd.
No 16, 3rd Main Road, Sakamma Garden,
Behind Old Shanti theatre, Basavanagudi,
Bangalore – 560 004, INDIA.
Phone : +91-80-2654 3777 / 3290 0854
Fax : +91-80-2664 6944

Email : info@milleniumsynergy.com

14. SunKon Energy – 10 MW Solar PV Power Plant

  • Project Location : Surendranagar district of North-West Gujarat
  • 25 year PPA (Power Purchase Agreement) with Gujarat Urja Vikas Nigam
  • Project is in the advanced stage of starting construction of this solar power plant.
  • Plant to be commissioned by March 2011.
  • The state transmission utility in Gujarat, GETCO will create the required infrastructure for the plant and all the necessary clearances have been received.

Contact :
SunKon Energy
Corporate Office
A-401, Oberoi Chambers
New Link Road, Andheri (W)
Mumbai 400 053, India
T : +91-22-26744375 / 6
F : +91-22-26744377
E : info@sunkon.co.in

15. Waaree Energies – 10 MW Solar Power Project

  • PPA Signed with Gujarat Urja Vikas Nigam
  • EPC Contractor : Inhouse

Contact :
Waaree Energies Pvt. Ltd.
36, Damji Shamji Industrial Complex,
off. Mahakali Caves road,
Andheri (East), Mumbai-400093,
India
Tel : +91-22-66963030/26874778
Fax : +91-22-26873613
Email : infosolar@waaree.com

http://www.waareeenergies.com

16. ZEBASOLAR – 10 MW Solar PV Power Plant

  • The project involves an investment of 35 million euro
  • This plant will have an annual power production of 16.37 million kWh, and a franchised operation term of 25 years.
  • PPA Signed with Gujarat Urja Vikas Nigam
  • All PV systems will be PV tracker panels, installed on land. ZEBASOLAR is in the process of setting up the GUJARAT joint venture company and confirming the EPC contract.

Contact :
Zeba Solar Pvt Ltd
Administrative HQ
79 Jolly Maker Chambers II
7th Floor
Nariman Point, Mumbai 40002
Office +91-22.66325007
Fax +91-22.66325222
email info@zebasolar.com

No related posts.