Around five to six more power plants are expected to begin operations in Gujarat soon.
|
Need New Projects Info? Newly Announced Projects Projects in Pipeline Complete Details, Address, Email, Telephone Key Personnel's Name Excel Sheet ,
Twice a Month |
State Energy minister Saurabh Patel said that more than 3,000 mw of conventional power generation capacity is likely to be commissioned in the coming few months.
“The state’s power generation capacity will increase from current 14,500 mw to close to 18,000 mw with commissioning of these projects. This will be a significant capacity addition in a very short period,” said Patel.
According to reports, Gujarat State Energy Generation (GSEG)’s 360 mw gas-based power plant at Hazira is ready for commissioning and could start power generation any day now. The 350 mw gas-based power plant of GSPC Pipavav Power Company at Pipavav is also nearing completion and is expected to be commissioned soon.
Gujarat State Electricity Corporation Limited’s (GSECL) 500 mw coal-based power plant at Ukai and Essar Power’s 600 mw power plant at Salaya are also expected to be commissioned in near future.
Related posts:
- Tripura plant set to start production
- Gujarat Identifies six sites for nuclear power plants.
- Essar Power reinstate PPA with Gujarat
- Gujarat eyes more power generation capacity
- Power Grid allots Rs 5k cr for transmission network in Gujarat
- MP to start 2 new units in 2012
- Greenfield Nuclear Power Plants – An Outlook
- Tidal Power Project in Gujarat.