Status of Food Parks in Karnataka
lnnova Agri-Bio Park
Project Location : Malur, Distt.-Kolar
Project Cost : Rs.1800 Lakhs
Approved Grant : Rs.400 Lakhs
Current Status : There was a change of Implementing Agency from Karnataka Industrial Areas Development Board (KIADB) initially to Food Karnataka Ltd. (FKL) formed by Karnataka Government later on. Implementation got delayed due to this change over. As per the latest progress report, the expenditure incurred on the project is Rs. 1492.50 lakhs
Green Food Park Ltd
Project Location : Bagalkot
Project cost : Rs.1859 Lakhs
Approved Grant : Rs.400 Lakhs
Current Status : As per the latest progress report, Rs. 913.75 lakhs has been incurred on the project by Implementing Agency. For release of third instalment, 75% of project cost should be incurred on the project which is yet to be achieved.
Jewargi Agro Food Park Ltd
Project Location : Jewargi
Project Cost : Rs.1793 Lakhs
Approved Grant : Rs.400 Lakhs
Current Status : Implementation of the project was delayed for almost 7 years due to some court case relating to acquisition of land. Now land has been acquired. As per the latest progress report the expenditure incurred on the project is Rs. 510.81 lakhs only.
Akshay Food Park Limited
Project Location : Hiriyur
Project Cost : Rs.1639 Lakhs
Approved Grant : Rs.400 Lakhs
Current Status : After fulfillment of prescribed conditions as per the schemes guidelines, 3rd instalment of grant has been released on 21.06.2010.